Project Summary

To meet increasing shipping needs and relieve the aging bridge built in 1899 over the Salt Fork of the Arkansas River near Ponca City, OK, construction of the $14-million BNSF project began in 2013. TranSystems completed the design and construction management for the new single-tracked, 7-span, 587-foot bridge including three 127- foot through plate girder spans, two 62-foot steel deck plate girder spans and three pre-stressed concrete spans. The existing bridge consisted of three 127-foot through truss spans with 48-foot deck plate girder approach spans.

Project Highlights

  • Design and construction management for 1899 bridge
  • Increase shipping needs and life span
 